Interroll RFQ Data Sheet: a compact checklist for warehouse automation RFQs

Use this page when your team already knows the loads, flows, interfaces and acceptance targets. Interroll keeps the checklist short so capital reviewers can compare modular conveyors, rollers, drum motors and crossbelt sorters against the same evidence classes. Fields below are intake scaffolding—not certified performance guarantees for a named model.

Requirements table

Interroll RFQ fields that must be filled before module comparison

Leave a cell blank only when the assumption is explicitly deferred—and name who owns the deferred decision.

RFQ field What to provide Why Interroll asks Evidence class
Load unit Carton, tote or pallet dimensions, weight bands, overhang rules Sets roller pitch, belt selection and crush limits Mechanical / application
SKU / order profile Active SKU depth, lines per order, velocity classes Drives induction balance and divert pressure Operations data
Peak rate & window Design rate, peak factor, duration, recovery time Prevents brochure rates from becoming design rates Throughput validation
Interfaces WMS / WCS / WES / PLC / sorter owners and timeouts Names restart authority and alarm routes Controls matrix
Site constraints Mezzanine clearances, floor quality, power, brownfield cutover windows Changes access, duty cycle and staging options Site / commissioning
Exception patterns Jams, mis-reads, recirculation surges already observed Sizes buffers and fallback lanes Operations / recovery
Acceptance witnesses FAT/SAT roles for divert samples and alarm checks Keeps go-live evidence challengeable FAT / SAT
Pre-submit checklist

Confirm these Interroll RFQ items before you hit send

Standards such as ISO 13849-1, ISO 12100 or the EU Machinery Directive may appear as review topics in project documents. They are not presented here as Interroll product certificates. Issuer, scope and validity must be confirmed against the delivered configuration.

Limits this checklist will not invent

Interroll will not convert an incomplete peak window into a guaranteed units-per-hour claim. Fixed conveyor modules may outperform flexible robotics on stable parcel profiles, yet they can reduce layout agility when SKU mix or client contracts change mid-season. Centralized WCS optimization can conflict with modular lane isolation during brownfield cutover—state which objective wins before FAT scripts freeze. Availability percentages, divert accuracy and interface cycle times are only meaningful with sample size, load mix and timeout ownership attached.

Submit the Interroll RFQ Data Sheet package

Send the completed checklist with attachments listed above. Interroll will reply with missing fields, deferred owners and the next acceptance gate to freeze—not a brochure rate detached from your peak window.